09 October 2023

The progress of works on the regional road DW 513 Lidzbark Warmiński – Wozławki

Tydzień pełen wydarzeń

The level of progress in the implementation of the regional road on section Lidzbark Warmiński – Wozławki at the end of September 2023 reached approx. 30%. The investment focuses on the extension of the regional road DW Nr. 513 and it is being conducted in stages. The works involve the demolition of the existing road and the construction of a new structure, mostly located within the footprint of the old road.

The total value of the agreement is PLN 145 million net, and the investor is the Voivodship Road Authority in Olsztyn. The agreement was signed on 30 March 2022. The road being expanded by Unibep’s Infrastructure Branch, is 20 kilometres long and it is classified as G-class road.

On this section, teams are simultaneously working on various aspects of construction, such as earthworks, finishing works, asphalt, power, telecommunications, sewage, and sanitation. The complexity of the project means that on certain sections the asphalt surface has already been laid, while on others, soil reinforcement is in progress, involving the concrete piles and sand-and-gravel columns technology or soil replacement.

Lidzbarg 2 min

The involvement of people and use materials in the investment

The total use of materials during the implementation of the investment is significant. On a twenty-kilometre section of the investment, the use of materials will total to 680 thousand tons of fill materials, 120 thousand tons of crushed aggregate, and 90 thousand tons of asphalt mixes.

It is also worth noting that around 200 people are currently working on the project, including 20 engineering staff, including subcontractor employees.

“During the project implementation, most of all, we faced the consequences of the events from February 2022, which affected the financial aspects and the availability of workforce. Besides, typically for most traffic infrastructure projects, archaeological findings emerge, project-related issues arise demanding a solution, and changes occur during the course of the work,” said Robert Sikora, Contract Director in the Infrastructure Branch at Unibep

Lidzbarg 4 min 

Video coverage from the construction site


Let's be
in touch!

Newsletter

Monday Development sp. z o.o.Oddziału Infrastruktury Unibep SAUnibep SAUnidevelopment SAUnihouse SA

© 2022  UNIBEP S.A. All rights reserved.  | Design Sensorama

Save
Cookies user preferences
We use cookies to ensure you to get the best experience on our website. If you decline the use of cookies, this website may not function as expected.
Accept all
Decline all
Read more
Analytical cookies
These cookies are particularly intended to enable the website administrator to monitor the website traffic statistics, as well as the sources of traffic. Such data is typically collected anonymously.
Google Analytics
Accept
Decline
Niezbędne
Essential cookies
These cookies are necessary for the correct operation of the website and therefore cannot be disabled on this level; the use of these cookies does not involve the processing of personal data. While you can disable them via your browser settings, doing so may prevent the website from working normally.
Accept
Decline
Functional
Tools used to give you more features when navigating on the website, this can include social sharing.
AddThis
Accept
Decline