02 June 2025

Progress visible in the field – Construction update S19 Krynice – Dobrzyniewo – Białystok Zachód

The S19 expressway on the Krynice – Dobrzyniewo – Białystok Zachód section is a key investment for the Podlasie region, carried out by a consortium of companies comprising PORR SA and Infrastructure Branch of Unibep SA, as part of the international transport corridor Via Carpatia. This strategic section will connect the north and south of Europe, supporting economic development and regional integration. Construction began in March 2024, and the completion is scheduled for the second quarter of 2026.

This is one of the key infrastructure investments on the eastern map of Poland. The investment is not only an important part of the European road network but also an example of a technologically complex engineering project adapted to local terrain and social conditions. From the general contractor’s perspective, this task demands the highest level of expertise, flexibility, and commitment from a team that combines experience with a sense of responsibility for the region’s future.

The work progress it is closer than further along

The investment is currently undergoing intensive construction works. On the main road section, a significant portion of earthworks and crushed stone road foundations has already been completed. The progress of bituminous bases made from mineral-asphalt mixtures has exceeded 70%, and the finishing works phase, along with the reconstruction of the crossroads intersecting the route, is now on the horizon. Although the schedule is tight, all activities are progressing according to plan, thanks to effective work organisation and continuous coordination between the technical, logistical, and supervisory teams.

Terrain-adapted bespoke engineering

The complexity of the investment is especially evident where the route intersects with existing infrastructure — national roads, a railway line, and the Supraśl and Biała rivers. These are the sections that require precise safety measures and often the execution of works under partially maintained traffic. Another challenge lies in the variable ground conditions — the presence of non-load-bearing soils, a high groundwater level, and sections containing organic material. In response to these challenges, advanced geotechnical solutions have been implemented: vertical drains to accelerate consolidation, surcharge embankments, as well as foundations for bridge and engineering structures set on CFA piles and precast concrete piles — solutions tailored to the specific geology of the area.

Environment in the spotlight

The route runs through areas of exceptional natural value, including the Knyszyńska Forest Landscape Park and the protection zone of the Jurowce–Wasilków underground water intake, which supplies Białystok with drinking water. Environmental protection is an integral part of the investment — the route includes wildlife crossings, noise barriers, retention basins, and compensatory green belts. The drainage system has been designed with the protection of groundwater and surface water quality in mind. All activities are carried out under strict environmental supervision, in accordance with rigorous environmental guidelines.

People who build the future

Currently, over 200 people are working on the construction site — a team of engineers, operators, logistics staff, and specialists who ensure precision, safety, and quality in the tasks carried out every day. The organisation of work resembles the operation of a large mechanism — equipment, deliveries, schedule, and supervision must function in complete synchronisation.

“Daily telephone communication is so intense that the construction site is often compared to a call centre except instead of headsets, there are helmets, and instead of desks, excavators and rollers,” says Sebastian Babiński, Construction Engineer.

The complexity of the project requires not only excellent planning but also a collaborative partnership between the contractor, investor, designer, and project supervision. The key is open communication, quick response to unforeseen situations, and shared responsibility for quality and timeliness. During the implementation phase, design adjustments were also made — based on local geotechnical assessments — which allowed for further optimisation of costs and technology.

Commitment visible every day

The people involved in the construction of this section bring not only knowledge and experience but also personal pride and a sense of mission to the project. For many team members, this is more than just another construction project. It is the awareness that their work is creating infrastructure that genuinely changes the lives of thousands of people. As Sebastian Babiński highlights: “This is not just a route it is infrastructure that will change the rhythm of life for thousands of people. We feel that we are leaving behind something lasting something that truly matters.”

 


Let's be
in touch!

Newsletter

Monday Development sp. z o.o.Oddziału Infrastruktury Unibep SAUnibep SAUnidevelopment SAUnihouse SA

© 2022  UNIBEP S.A. All rights reserved.  | Design Sensorama

Cookies user preferences
We use cookies to ensure you to get the best experience on our website. If you decline the use of cookies, this website may not function as expected.
Accept all
Decline all
Read more
Analytical cookies
These cookies are particularly intended to enable the website administrator to monitor the website traffic statistics, as well as the sources of traffic. Such data is typically collected anonymously.
Google Analytics
Accept
Decline
Niezbędne
Essential cookies
These cookies are necessary for the correct operation of the website and therefore cannot be disabled on this level; the use of these cookies does not involve the processing of personal data. While you can disable them via your browser settings, doing so may prevent the website from working normally.
Accept
Decline
Functional
Tools used to give you more features when navigating on the website, this can include social sharing.
AddThis
Accept
Decline
Save