Unibep Group

Investor relations

71/2020 | Update of information on the agreement for implementation of the next stage of a residential investment being a joint construction project in the Ursus district in Warsaw

2020.12.10 09:14

In reference to the content of the current report No. 45/2020 of 2 September 2020 on the conclusion with URSA SKY Smart City Sp. z o.o. Sp. k. with its registered office in Warsaw (Ordering Party) of the agreement for implementation of construction works in general contracting system in the area between the streets of Silnikowa, Herbu Oksza and Quo Vadis as part of the project called URSA SKY (Investment), the Management Board of UNIBEP SA informs that on 10 December 2020 received from the Ordering Party a written order the to commence the works on the second stage.

Attachments:
Access this URL (https://unibep.pl/attachments/article/3705/Rb_71_2020.pdf)71-2020